MERCANTILE DRIVE PAVEMENT REHABILITATION PROJECT

Pic3.jpg

Location: Rancho Cordova, CA

Client: City of Rancho Cordova Department of Public Works

Construction Value: $1.3 Million

Services Provided: Full Construction Management Services

The project consisted of street, sidewalk, and driveway improvements for approximately 1 ½ miles of Mercantile Drive, between Folsom Boulevard and Sunrise Gold Circle.  Construction improvements included:  the installation of storm drain laterals and drain inlets and large diameter manholes (60” – 90”), AC pavement leveling course and 2” AC overlay, base failure repair, removal and replacement of curb, gutter, sidewalk, and driveways, Type 2 slurry, traffic signage and striping.  SAI met with over 20 property owners and individual businesses to coordinate access, and reduce impacts during driveway replacements. SAI and their contractors to coordinate their driveway replacement so it did not impact the overall project. SAI also met with property owners to replace landscaping after improvements were completed.